Question Detail
5 men and 2 boys working together can do four times as much work as a man and a boy. Working capacity of man and boy is in the ratio
- 1:2
- 1:3
- 2:1
- 2:3
Answer: Option C
Explanation:
Let 1 man 1 day work = x
1 boy 1 day work = y
then 5x + 2y = 4(x+y)
=> x = 2y
=> x/y = 2/1
=> x:y = 2:1
1. 4 men and 6 women finish a job in 8 days, while 3 men and 7 women finish it in 10 days. In how many days will 10 women working together finish it ?
- 30 days
- 40 days
- 50 days
- 60 days
Answer: Option B
Explanation:
Let 1 man's 1 day work = x
and 1 woman's 1 days work = y.
Then, 4x + 6y = 1/8
and 3x+7y = 1/10
solving, we get y = 1/400 [means work done by a woman in 1 day]
10 women 1 day work = 10/400 = 1/40
10 women will finish the work in 40 days
2. To complete a work A and B takes 8 days, B and C takes 12 days, A,B and C takes 6 days. How much time A and C will take
- 24 days
- 16 days
- 12 days
- 8 days
Answer: Option D
Explanation:
A+B 1 day work = 1/8
B+C 1 day work = 1/12
A+B+C 1 day work = 1/6
We can get A work by (A+B+C)-(B+C)
And C by (A+B+C)-(A+B)
So A 1 day work =
\begin{aligned}
\frac{1}{6}- \frac{1}{12} \\
= \frac{1}{12}
\end{aligned}
Similarly C 1 day work =
\begin{aligned}
\frac{1}{6}- \frac{1}{8} \\
= \frac{4-3}{24} \\
= \frac{1}{24}
\end{aligned}
So A and C 1 day work =
\begin{aligned}
\frac{1}{12} + \frac{1}{24} \\
= \frac{3}{24} \\
= \frac{1}{8}
\end{aligned}
So A and C can together do this work in 8 days
3. A is twice as good as workman as B and together they finish a piece of work in 18 days. In how many days will B alone finish the work.
- 27 days
- 54 days
- 56 days
- 68 days
Answer: Option B
Explanation:
As per question, A do twice the work as done by B.
So A:B = 2:1
Also (A+B) one day work = 1/18
To get days in which B will finish the work, lets calculate work done by B in 1 day =
\begin{aligned}
=\left(\frac{1}{18}*\frac{1}{3} \right) \\
= \frac{1}{54}
\end{aligned}
[Please note we multiplied by 1/3 as per B share and total of ratio is 1/3]
So B will finish the work in 54 days
4. Worker A takes 8 hours to do a job. Worker B takes 10 hours to do a job. How long should it take both A and B, working together to do same job.
- \begin{aligned} \frac{4}{9} \end{aligned}
- \begin{aligned} 2\frac{4}{9} \end{aligned}
- \begin{aligned} 3\frac{4}{9} \end{aligned}
- \begin{aligned} 4\frac{4}{9} \end{aligned}
Answer: Option D
Explanation:
In this type of questions, first we need to calculate 1 hours work, then their collective work as,
A's 1 hour work is 1/8
B's 1 hour work is 1/10
(A+B)'s 1 hour work = 1/8 + 1/10
= 9/40
So both will finish the work in 40/9 hours
= \begin{aligned} 4\frac{4}{9} \end{aligned}
5. A and B can together complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work ?
- 4 days
- 5 days
- 6 days
- 7 days
Answer: Option C
Explanation:
(A+B)'s 1 day work = 1/4
A's 1 day work = 1/12
B's 1 day work =
\begin{aligned}
\left( \frac{1}{4} - \frac{1}{12} \right) \\
= \frac{3-1}{12} \\
= \frac{1}{6} \\
\end{aligned}
So B alone can complete the work in 6 days