- Home
- Quantitative
- English
- Reasoning
- IT Officer
- Programming
-
Computer
- Computer Awareness Questions Answers - Set 1
- Computer Awareness Questions Answers - Set 2
- Important Abbreviations Computer Awareness Questions Answers
- Important File Extensions Questions Answers
- Computer System Architecture Questions Answers
- MS Office Questions Answers
- MS Excel Questions Answers
- MS PowerPoint Questions Answers
-
GK
- Geography Questions Answers
- Indian History Questions Answers
- World History Questions Answers
- Indian Economy Questions Answers
- Indian Polity and Constitution
- Physics Questions Answers
- Chemistry Questions Answers
- Biology Questions Answers
- First In India
- First In World
- Longest and Largest
- Books and Authors
- Important Days of year
- Countries and Capitals
- Inventions and Inventors
-
Current Affairs
- Current Affairs
- Current Affairs 2018
- Current Affairs 2018 - 2019 PDF
- Current Affairs August 2019
- Current Affairs July 2019
- Current Affairs June 2019
- Current Affairs May 2019
- Current Affairs April 2019
- Current Affairs March 2019
- Current Affairs February 2019
- Current Affairs January 2019
- Current Affairs December 2018
- Current Affairs November 2018
- Current Affairs October 2018
- Current Affairs September 2018
- Govt Jobs
- Exams
- Online Quiz
- You are here
- Home
- Quantitative Aptitude
- Arithmetic Aptitude Questions Answers
- Time and Work Questions Answers
- Aptitude Question
- Current Affairs 2019
- Current Affairs 2018
- Current Affairs December 2018
- Current Affairs November 2018
- Current Affairs October 2018
- Current Affairs September 2018
- Current Affairs August 2018
- Current Affairs July 2018
- Current Affairs June 2018
- Current Affairs May 2018
- Current Affairs April 2018
- Current Affairs March 2018
- Current Affairs February 2018
- Current Affairs January 2018
- Current Affairs 2018
- Current Affairs PDF
- Current Affairs PDF Download
- Current Affairs July 2019 PDF
- Current Affairs June 2019 PDF
- Current Affairs May 2019 PDF
- Current Affairs April 2019 PDF
- Current Affairs March 2019 PDF
- Current Affairs February 2019 PDF
- Current Affairs January 2019 PDF
- Current Affairs December 2018 PDF
- Current Affairs November 2018 PDF
- Current Affairs October 2018 PDF
- Current Affairs September 2018 PDF
- Current Affairs August 2018 PDF
- Current Affairs July 2018 PDF
- Current Affairs June 2018 PDF
- Current Affairs May 2018 PDF
- Current Affairs April 2018 PDF
- Current Affairs March 2018 PDF
- Current Affairs February 2018 PDF
- Current Affairs January 2018 PDF
Question Detail
A does half as much work as B in three-fourth of the time. If together they take 18 days to complete the work, how much time shall B take to do it
- 40 days
- 35 days
- 30 days
- 25 days
Answer: Option C
Explanation:
Suppose B takes x dáys to do the work.
As per question A will take
\begin{aligned}
2* \frac{3}{4} * x = \frac{3x}{2}days
\end{aligned}
(A+B)s 1 days work= 1/18
1/x + 2/3x = 1/18 or x = 30 days
1. A can finish a work in 18 days and B can do same work in half the time taken by A. then working together, what part of same work they can finish in a day
- 1\5
- 1\6
- 1\7
- 1\8
Answer: Option B
Explanation:
Please note in this question, we need to answer part of work for a day rather than complete work. It was worth mentioning here because many do mistake at this point in hurry to solve the question
So lets solve now,
A's 1 day work = 1/18
B's 1 day work = 1/9 [because B take half time than A]
(A+B)'s one day work =
\begin{aligned}
\left(\frac{1}{18}+\frac{1}{9} \right) \\
=\left(\frac{1+2}{18} \right) \\
= \frac{1}{6}
\end{aligned}
So in one day 1/6 work will be done.
2. A completes 80% of a work in 20 days. Then B also joins and A and B together finish the remaining work in 3 days. How long does it need for B if he alone completes the work?
- \begin{aligned} 35\frac{1}{2} \end{aligned}
- \begin{aligned} 36\frac{1}{2} \end{aligned}
- \begin{aligned} 37\frac{1}{2} \end{aligned}
- \begin{aligned} 38\frac{1}{2} \end{aligned}
Answer: Option C
Explanation:
Work done by A in 20 days = 80/100 = 8/10 = 4/5
Work done by A in 1 day = (4/5) / 20 = 4/100 = 1/25 --- (1)
Work done by A and B in 3 days = 20/100 = 1/5 (Because remaining 20% is done in 3 days by A and B)
Work done by A and B in 1 day = 1/15 ---(2)
Work done by B in 1 day = 1/15 – 1/25 = 2/75
=> B can complete the work in 75/2 days = 37 (1/2) days
3. 4 men and 6 women finish a job in 8 days, while 3 men and 7 women finish it in 10 days. In how many days will 10 women working together finish it ?
- 30 days
- 40 days
- 50 days
- 60 days
Answer: Option B
Explanation:
Let 1 man's 1 day work = x
and 1 woman's 1 days work = y.
Then, 4x + 6y = 1/8
and 3x+7y = 1/10
solving, we get y = 1/400 [means work done by a woman in 1 day]
10 women 1 day work = 10/400 = 1/40
10 women will finish the work in 40 days
4. A does half as much work as B in three-fourth of the time. If together they take 18 days to complete the work, how much time shall B take to do it
- 40 days
- 35 days
- 30 days
- 25 days
Answer: Option C
Explanation:
Suppose B takes x dáys to do the work.
As per question A will take
\begin{aligned}
2* \frac{3}{4} * x = \frac{3x}{2}days
\end{aligned}
(A+B)s 1 days work= 1/18
1/x + 2/3x = 1/18 or x = 30 days
5. A is thrice as good a workman as B and takes 10 days less to do a piece of work than B takes. B alone can do the whole work in
- 15 days
- 10 days
- 9 days
- 8 days
Answer: Option A
Explanation:
Ratio of times taken by A and B = 1:3
Means B will take 3 times which A will do in 1 time
If difference of time is 2 days, B takes 3 days
If difference of time is 10 days, B takes (3/2) * 10 =15 days
Thanks ! Your comment will be approved shortly !
- Copyright 2014 - All rights reserved
- Terms Of Use & Privacy Policy
- Contact Us
- Copyright