A is thrice as good a workman as B and takes 10 days less to do a piece of work than B takes. B alone can do the whole work in

  • 15 days
  • 10 days
  • 9 days
  • 8 days
Similar Questions :

1. A does half as much work as B in three-fourth of the time. If together they take 18 days to complete the work, how much time shall B take to do it

  • 40 days
  • 35 days
  • 30 days
  • 25 days

2. Worker A takes 8 hours to do a job. Worker B takes 10 hours to do a job. How long should it take both A and B, working together to do same job.

  • \begin{aligned} \frac{4}{9} \end{aligned}
  • \begin{aligned} 2\frac{4}{9} \end{aligned}
  • \begin{aligned} 3\frac{4}{9} \end{aligned}
  • \begin{aligned} 4\frac{4}{9} \end{aligned}

3. A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C

  • Rs. 300
  • Rs. 400
  • Rs. 500
  • Rs. 600

4. A can finish a work in 18 days and B can do same work in half the time taken by A. then working together, what part of same work they can finish in a day

  • 1\5
  • 1\6
  • 1\7
  • 1\8

5. A can do a piece of work in 4 hours . A and C together can do it in just 2 hours, while B and C together need 3 hours to finish the same work. In how many hours B can complete the work ?

  • 10 hours
  • 12 hours
  • 16 hours
  • 18 hours
Read more from - Time and Work Questions Answers
Post a comment

  • sindhu 8 years ago

    could anyone explain 5th question more clearly

  • Anirban Majumder 9 years ago

    {K/(K-1)}* LESS DAYS
    {3/(3-1)*10}
    (3/2)*10
    3*5
    15DAYS

  • Anirban Majumder 9 years ago

    short cut :-

    times less/ (K-1) where K is efficiency

    therefore 10/ (3-1)

    =5 hence A takes 5 days to do the work {& which is 10 days less than that of B}

    so B takes 10+5 = 15 days

  • manasa 10 years ago

    could you please explain this prob.

    mastguru 10 years ago replied

    Hello Manasa,

    In this type question where working capacity is given and we need to calculate the time.

    If you do certain work faster than me, then you will take less time than me, right !

    Now A is three times better workman than B.

    So, the work which B will do in 3 days, A will do in 1 day.

    So Ratio of time is 1:3

    If difference of time is 2 days, B takes 3 days (Please note from ratio 3 - 1 = 2)

    If difference of time is 10 days, B takes (3/2) * 10 =15 days.

    Thanks