To complete a work A and B takes 8 days, B and C takes 12 days, A,B and C takes 6 days. How much time A and C will take

  • 24 days
  • 16 days
  • 12 days
  • 8 days
Similar Questions :

1. A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C

  • Rs. 300
  • Rs. 400
  • Rs. 500
  • Rs. 600

2. 5 men and 2 boys working together can do four times as much work as a man and a boy. Working capacity of man and boy is in the ratio

  • 1:2
  • 1:3
  • 2:1
  • 2:3

3. A can do a piece of work in 15 days and B alone can do it in 10 days. B works at it for 5 days and then leaves. A alone can finish the remaining work in

  • 5 days
  • 6 days
  • 7.5 days
  • 8.5 days

4. A man can do a piece of work in 5 days, but with the help of his son he can do it in 3 days. In what time can the son do it alone ?

  • \begin{aligned} 7\frac{1}{2}days \end{aligned}
  • \begin{aligned} 6\frac{1}{2}days \end{aligned}
  • \begin{aligned} 5\frac{1}{2}days \end{aligned}
  • \begin{aligned} 4\frac{1}{2}days \end{aligned}

5. 4 men and 6 women finish a job in 8 days, while 3 men and 7 women finish it in 10 days. In how many days will 10 women working together finish it ?

  • 30 days
  • 40 days
  • 50 days
  • 60 days
Read more from - Time and Work Questions Answers
Post a comment