To complete a work A and B takes 8 days, B and C takes 12 days, A,B and C takes 6 days. How much time A and C will take

  • 24 days
  • 16 days
  • 12 days
  • 8 days
Similar Questions :

1. A piece of work can be done by 6 men and 5 women in 6 days or 3 men and 4 women in 10 days. It can be done by 9 men and 15 women in how many days ?

  • 3 days
  • 4 days
  • 5 days
  • 6 days

2. 5 men and 2 boys working together can do four times as much work as a man and a boy. Working capacity of man and boy is in the ratio

  • 1:2
  • 1:3
  • 2:1
  • 2:3

3. A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C

  • Rs. 300
  • Rs. 400
  • Rs. 500
  • Rs. 600

4. A alone can complete a work in 16 days and B alone can do in 12 days. Starting with A, they work on alternate days. The total work will be completed in

  • \begin{aligned} 13\frac{1}{4} \end{aligned}
  • \begin{aligned} 13\frac{1}{2} \end{aligned}
  • \begin{aligned} 13\frac{3}{4} \end{aligned}
  • \begin{aligned} 13\frac{4}{4} \end{aligned}

5. A and B can together complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work ?

  • 4 days
  • 5 days
  • 6 days
  • 7 days
Read more from - Time and Work Questions Answers